This is a proposed operating model for review, not a claim that every record or action is already built in v9.346. The horizontal axis is logical sequence; no clock time is implied.

Start here

This is a proposed operating model for review. Follow the manufacturing process first. The software details are optional and stay out of the way until you ask for them.

  1. Follow the processRead the manufacturing steps from left to right, or use Walk the cycle to see one stage at a time.
  2. Open a plain explanationSelect any stage or process step for a plain-language explanation of who acts and what happens.
  3. Add the software viewTurn on System support and controls only when you want to review application behavior or future safeguards.

System support and controls add the technical record names, current-versus-proposed status labels, and source references. The manufacturing process stays visible either way.

The RH manufacturing scheduling process, start to finish

RH gathers the work and plant facts, checks that the inputs are ready, builds and reviews the production schedule, releases one schedule to the floor, performs the work, records what happened, resolves differences, and closes the planning effort.

Each step below names what the reader is looking at and the main result it produces. Select a stage in the canvas underneath for the full explanation.

    In short Orders and plant facts readiness check draft production schedule reviewed schedule official floor schedule work performed actual results differences resolved and cycle closed

    The full cycle as one picture

    Each row is a participant. Rows with a person mark are people, the row with a chip mark is the deterministic system, and the middle row is the information and schedule that gains authority as it moves from one person to the next. Step through the stages, or follow one participant to see only what they touch.

    Tip: Select a shape to open its plain-language meaning, example, and next step. Select a stage, then use Stage details for the stage-level explanation.

    RH may prepare tomorrow's schedule while the floor still performs today's

    Four parts of the work move at the same time. While the scheduler prepares and reviews the next schedule, the floor keeps performing the official schedule that is already released. This table shows what each part is doing at each stage.

    One official schedule, many views

    The floor and every plan-based view should show the same official schedule. Forecasts and actual results must be labeled separately. Today two views build their own schedule instead of showing the released one, so this rule is not yet true.

    Current-plan marker → Plan N

    Official released plan

    Locked lines · unique identifier and hash · release actor and time · replaces Plan N-1 only when a newer plan is released

    Finding to resolve before cutover. Weekly Plan and Daily Plan build their own schedule from the open orders instead of only showing the released plan. Until that is corrected, the floor and reports cannot be guaranteed to show the same official schedule.

    Plain-language key

    The exact technical names remain available in the detail panel and canonical specifications. This key explains the terms used in the review package.

    Draft plan (candidate)The optimizer's proposed plan. The floor does not follow it until it is released.
    Official released planThe one current plan the floor and reports must use.
    Recorded outcome (disposition)What happens next to an item or block: for example, schedule, correct, hold, resume, or cancel.
    Actual work recordedWhat was actually produced, when it happened, and any difference from the plan.
    Approve completionCheck a submitted completion before inventory, shipment, booking, or reporting effects can post.
    Compare and explain differencesCheck the plan, actual work, inventory, customer status, shipment, and reports before closing.

    How to read this